Top 10 Fitout Mistakes to Avoid (ACT Landlord Tips)
Published by Adeel Virk
Adeel is a founder & project manager at Virk Construction Management, delivering ethical, high-quality residential and commercial projects in NSW and Canberra.
Most fitout advice starts with colours, desks and breakout zones. That order is backwards. In Canberra, the building decides what is possible long before a designer picks a finish. Power, air handling, fire systems and lease terms draw the real boundaries. A tenant who ignores them pays twice, once in rework and again at lease end. A landlord who ignores them struggles to relet. This post covers ten fitout mistakes seen across ACT offices, with a technical check for each one and landlord tips where they matter. One idea runs through the list: treat capacity as the first design decision.
Office vacancy rate, mid 2026 (percent)
Vacancy rate (%)
1. Designing Before Checking Base Building Capacity
A designer can sketch a lovely meeting room in an afternoon. Whether the building can serve it is another question. Spare electrical capacity, riser space, air handling, and ceiling void depth all belong to the base building, and tenants rarely see them until a consultant asks.
Floors matter too. General office floors are typically designed for about 3 kPa, and dense storage can exceed that. Boring checks, yes. Expensive to skip, also yes.
Owners who publish a services capacity schedule in the leasing pack shorten negotiations and avoid late surprises.
2. Ignoring the Make Good Clause Until Exit
Make good decides what you pay on the way out. Some clauses demand removal back to base building condition. Others accept a lighter handover. If a tenant does not complete the work, the landlord can hire contractors and draw the cost from the bank guarantee. For retail leases, the ACT disclosure statement carries a section on finishes and make good details, and it must reach the tenant at least 14 days before signing.
A generous lease incentive can vanish under an aggressive reinstatement clause, so negotiate both together and let a solicitor read the wording. Owners should describe the end condition with a schedule and photographs. Vague wording is how disputes start.
Planning office fitouts in Canberra?
Talk to Virk Construction Management before you sign the lease, and get capacity checks, approvals, and handover managed from day one.
Talk to Our Team3. Treating Landlord Consent as a Formality
Approval from the owner is a process, not a signature. A typical Canberra tenant guide lists concept design approval, detailed design approval, then builder and certifier appointment, with written sign-off before work starts. Submit late, and the programme slips by weeks. Building manuals often cover after-hours work, lift bookings, hoisting, signage and services shutdowns, so read yours before pricing anything.
What helps on the owner side? One checklist and a fixed review window. Tenants notice the difference.
4. Starting Work Without the Right Approvals
Fitout compliance in the ACT begins with a building approval from a licensed certifier under the Building Act 2004. The certifier issues a commencement notice before construction and signs a certificate of completion afterwards. Asbestos advice must also accompany the approval. That matters in older buildings.
Some minor works are exempt. Get the certifier to confirm that in writing, not over the phone. Owners who keep drawings and asbestos registers current make every review faster.
5. Moving Walls Without Rechecking Fire Systems
Every new partition changes how smoke, heat and water behave. Before the ceiling closes, confirm four things:
Sprinkler heads still give compliant coverage under AS 2118.1.
Detectors suit the new rooms under AS 1670.1.
Emergency lighting and exit signs meet AS/NZS 2293.1.
Travel distances to exits still pass the National Construction Code.
A full height meeting room can block a path the original design relied on. Catch that on paper. Rework above a finished ceiling costs far more, which is why many owners ask for fire services sign-off first.
6. Under Planning Heating, Cooling and Power
Canberra sits in climate zone 7 under the National Construction Code. Think frosty mornings, hot dry summers and big daily swings. A meeting room full of people and screens overheats while perimeter desks stay cold. Recheck zoning after every layout change.
Power has shifted too. Since 8 December 2023, new gas network connections have been prevented in commercial zones. Hot water, heating and cooking now run on electricity, which lifts switchboard and cable demand. The Territory has committed to phasing gas out before 2045, so spare switchboard and riser capacity is a sound bet for any building owner.
7. Treating Acoustics as Decoration
Open plans look fine in drawings and sound harsh in use. Partitions that stop at the ceiling tile let speech travel through the void. Meeting rooms need walls running to the slab above, sealed penetrations and doors with seals.
Many designers aim for roughly Rw 45 or higher for meeting rooms, and more for boardrooms. Strong office fitout designs mix absorption, zoning and a few quiet rooms that people actually use. Test one sample partition detail before you build the whole floor.
8. Ignoring Security Zones, or Over Specialising for Them
Canberra has a large pool of government and defence tenants. Some occupier briefs ask for premises meeting ASIO T4 requirements for a Zone 4 area, with Defence physical security certification. Even a Zone 2 perimeter can involve tamper-evident finishes, security grilles and access control. Plan the zone line early, because certification depends on construction detail. greenstreetnewsfdcbuilding
The trap for owners runs the other way. A heavily specialised suite is hard to relet when that tenant leaves. Spec suites offer a middle path. Virk Construction Management completed a spec office fitout where a 320 square metre tenancy was split into suites of 140 and 180 square metres.
9. Budgeting by the Square Metre Alone
Canberra office fitouts range from about $400 to over $2,500 per square metre, and a standard Category B fitout for 200 square metres typically costs $140,000 to $220,000. Those ranges are wide for a reason. Hidden lines include after-hours labour, services shutdowns, hoisting, certifier fees, and make good of earlier works.
Hold a contingency allowance, often around ten per cent, and protect it from upgrade requests. Category A and Category B scope also differ, so confirm which one each quote assumes. Owners offering a contribution should state a fixed figure and list what it covers. Vague contributions invite arguments.
10. Rushing the Timeline and Skipping the Handover Inspection
Most Canberra office fitouts take eight to sixteen weeks from design to practical completion. Joinery, glazing and switchgear often stretch the office fitout timeline because they set the critical path. Order them early where the risk is acceptable.
Then slow down at the end. Uneven air conditioning zoning is among the most common complaints in Canberra fitouts. Run every zone, test the fire systems, and work through a full defects checklist before accepting the space. Confirm the defect liability period, and collect as-built drawings, test certificates, and manuals. The next tenant, and the next owner, will ask for them.
A New Lens: The Exit Value Test
Here is a different way to judge every fitout decision. Before approving an item, ask whether the next tenant would pay for it. Then sort it into one of three bins.
Keep: items that add value for almost any tenant, such as good acoustics, efficient lighting, clean data pathways and accessible amenities.
Reuse: items that move or reconfigure easily, such as modular partitions, loose furniture and demountable joinery.
Remove: bespoke items that suit only one tenant, such as specialist signage, unusual finishes or secure rooms.
Landlords can apply the same test to incentives. Fund keep items willingly. Question remove items. Tenants can use it too, because it cuts make good cost before that cost exists. With vacancy above one quarter, the next tenant will compare your space against many rivals. Exit value stops being theoretical very quickly.
Quick Reference Table: Mistakes, Technical Checks and Risk Owners
| # | Mistake | Technical Check | Main Risk Owner |
|---|---|---|---|
| 1 | Skipping capacity checks | Power, risers, floor loading | Tenant, then landlord |
| 2 | Ignoring make good | End condition schedule, bank guarantee | Tenant |
| 3 | Treating consent as a formality | Concept and detailed design sign off | Both |
| 4 | Missing approvals | Certifier, asbestos advice, completion certificate | Both |
| 5 | Unchecked fire systems | Sprinklers, detection, exits, emergency lighting | Tenant |
| 6 | Weak HVAC and power plan | Zoning, electric loads, switchboard | Both |
| 7 | Poor acoustics | Slab to slab walls, seals, ceiling void | Tenant |
| 8 | Security gaps or over specialising | Zone certification, relet flexibility | Landlord |
| 9 | Square metre budgeting only | Contingency, hidden cost lines | Tenant |
| 10 | Rushed timeline and handover | Lead times, defect inspection | Both |
A Five Question Check Before You Sign
What capacity does the base building offer, in writing?
What is the make good scope, and what secures it?
Which approvals apply, and who lodges them?
What is the programme, including long lead items?
Would the next tenant pay for this item?
Plan Your Fitout With Confidence
A good fitout starts with capacity checks and ends with an exit plan. Everything in between is detail, and detail is where money quietly disappears.